Blog‎ > ‎

August 10th, 2009

posted Aug 10, 2009, 4:08 PM by 1897 House   [ updated Aug 10, 2009, 5:20 PM ]
Good progress today on the electrical, plumbing and framing.  Doorway between the pantry and apartment was framed as well as sections of the kitchen.  Electricians started running wire in the basement, mud room, kitchen, first floor bath and office.  Plumbers continued their work on the second floor with hot water heat in the second and fourth bedrooms.  Boiler installation starts tomorrow.

There were, at any given time, as many six different subs working their way through the house.  

Siding removal subcontractor was supposed to be on-site this afternoon, but was a no-show.
Comments