Blog‎ > ‎

July 29th, 2009

posted Jul 29, 2009, 4:32 PM by 1897 House
End of day eight.  Early morning meeting with contractor, project manager and supervisor to review the verbal modifications and review status of work to date.  Hoping to get a full project plan to be able to know when the light at the end of the tunnel is the end and not a train.

Demolition continued today with the third and final doorway cut from the new laundry room on the second floor of the main section of the house into the apartment bathroom.  All went well but had to lose some cabinets that we had planned on keeping in order to line the door up with the one on the other side of the bathroom.  Now, for the first time ever, you can go directly to the second floor of the apartment from the main part of the house (through the jack and jill bathroom).  This is going to give us access to two full baths from the second floor.

The plumbers are making good progress with the hot water heat lines and the new water lines.
Comments