The word for today is "kitchen".  As in, countertops and backsplash.

Plumbers continued working on installing the new baseboard heaters and the painters spent another full day prepping the interior walls for paint which starts next Monday.

As it stands now, the painters will spend the next week painting the interior of the house.  Then the electricians will be on site the following Monday to finish the electrical trim and then hopefully mid-week, the hardwood floor guy will be here to spend three days finishing the floors.  This puts us into the third week of October to start to bring this to a close.