The smell of bondo permeating the entire house makes me fell like we're living in a body shop.  Thankfully, the smell of paint should start to replace it tomorrow.

Painters continuing their work on prepping the inside of the house.  Doing a great job filling cracks and nail holes.

Plumbers worked to get the apartment bathroom functional so they can begin demo on the only functional bathroom on Wednesday.  Goal is to have the new bathroom up and running on Tuesday.

HVAC guy was here for some reason, but not exactly certain as to why.  Spoke with him briefly while he was on the roof.  Hoping to test out the swamp coolers on Wednesday and then winterize them as it's now in the 50's and 60's during the day.

Trim finisher worked on the new first floor bathroom installing wainscoting on the walls.