Relatively quiet day on the renovation front.

Drywall crew was here early to finish up their part of the process.  City inspector was on-site around mid-day to inspect the drywall work as well as the electrical work in the main house that wasn't completed the last go round.  As far as I could tell, we are good to go with the mud guys starting tomorrow morning.

At our weekly meeting, the supervisor asked if the mud subs could work this weekend, both Saturday and Sunday.  While we are not looking forward to it, we agreed as we will then be in a position to start laying hardwood flooring in the kitchen next Monday which then means kitchen cabinets later the same week.

With everything in the house currently covered in a fine white dust, we might as well just hit it hard for the next few days and be done with it. 